“The work at the new headquarters is at an accelerated pace. An additional 1,000 workers have been brought to complete the project in a time bound manner with a total number of workers and technicians reaching 2,500," the official explained.
The committee supervising the works of the new headquarters has held several meetings with the companies involved in the project. Brig Dr al-Marri pointed out that an inspection tour was undertaken recently to follow up on the progress of the works. In June 2017, the Ministry of Interior (MoI) signed a contract for a project to construct a building of the Police College in the Mberik area on Salwa Road.
The contract includes constructing various buildings and facilities at an area of 624,000sq m. The first phase includes construction of 19 administrative and service buildings. These include four educational buildings, as well as student barracks, the administrative building, the sports complex, the platform and the main training field.